Office 02080501418 Mobile 07401439783 Email:makingspacebelowgroundltd@hotmail.com



Office number
03301271035
Home
Basements
Underpinning
Groundwork
Foundations
Testimonials
Lowering basement
Hand digging basements
Block And Beams
Form work
Waterproofing/Tanking
Structural Engineering
Gallery
contact
projects


Office number
03301271035
Home
Basements
Underpinning
Groundwork
Foundations
Testimonials
Lowering basement
Hand digging basements
Block And Beams
Form work
Waterproofing/Tanking
Structural Engineering
Gallery
contact
projects
More
  • Home
  • Basements
  • Underpinning
  • Groundwork
  • Foundations
  • Testimonials
  • Lowering basement
  • Hand digging basements
  • Block And Beams
  • Form work
  • Waterproofing/Tanking
  • Structural Engineering
  • Gallery
  • contact
  • projects
  • Home
  • Basements
  • Underpinning
  • Groundwork
  • Foundations
  • Testimonials
  • Lowering basement
  • Hand digging basements
  • Block And Beams
  • Form work
  • Waterproofing/Tanking
  • Structural Engineering
  • Gallery
  • contact
  • projects

NEW BASEMENT FOR MOSQUE AT MAZAHIRUL ULOOM, MILE END ROAD E14AA

 We reduced the ground 9.5 meters by 5.5 meters down to the depth of 3 meters Removal of main muck to be down no lower than the existing footings, until underpinning was completed. Underpinning was dug out in sequence, once dug out to the depth of 3 meters reinforcement bars where put in as shown on drawings. Thickness of retaining wall 300mm. The main vertical bars where H10 at 125 centers, giving a 50mm covering, H10 bars at 200 centers coming into the toe. The toe was dug out at 300 thickness and 1.9 meters in length. A 300 thick heel was put into the depth of 325, main bars to the heel to where H8 bars at 126 centers. Once reinforcement was in the holes, they where inspected by building control then shuttered up and strut to the bank. Concrete was poured and vibrated down. A 75mm gap was left for dry packing. 13 pins all told where underpinned in sequence as shown in the drawing.

COMPLETE DIG OUT OF NEW BASEMENT SHELL, UNDER EXISTING HOUSE IN Ilford IG14LE

We completed a new basement shell, under existing house, extending out under my garden.  2,200 sq foot in total. the job consisted of underpinning and forming the retaining walls. Putting in a new concrete slab, and digging out under neath my garden. The dig out under the garden was 6 meters by 10 meters.  The complete basement shell was completed and block and beam was done.  All concrete was poured in using C40 concrete and a concrete pump. All channels where dug out for waterproofing at a later stage and a pit was dug out ready for the pumps.

TRIAL PITS DUG AT OUR SIKH CENTER IN WEST LONDON

                   Trial pits dug out at our Sikh center in West Ealing.                                          Soil samples where taken by Making Space and sent away for testing.

BASEMENT UNDER HOUSE ADDING MUCH NEEDED SPACE

We excavated under the house and built a new basement. All underpinning was completed and new slabs completed, this was carried out following the structural engineers drawings.

We completed the excavation for a new basement for a two story extension to be built on top. We faced many issues with this project, and the structural drawings kept changing. We took 5 months to complete this in the end to the engineers satisfaction.

BASEMENT CONSTRUCTION. IN WEST LONDON

Lowering of 140m2 lower ground floor by 1500mm .

Internal steel structures Structural openings throughout .

Below ground drainage. Cavity drain membrane system Installation of sumps and pumps.

GROUNDWORK'S AT SUN MARK LTD GREEN-FORD UB6 8UH.

 Digging out of a 55,000 sq foot for new warehouse after there was a fire at the original ware house.We completed all the digging out and removal of soil from site.We completed all the pad stones, holding down bolts, sheet piles and deep drainage.All concreting was completed. this took a lot of concrete to complete.The cafe area at the ware house.We completed the following.Pilling, breaking down of the piles, ring beams and all the steel work.Again it took a large amount of concrete.All drainage and block and beam floors where completed.This was a 16 month contract.

  • Home
  • Basements
  • Underpinning
  • Groundwork
  • Foundations
  • Testimonials
  • Hand digging basements
  • Block And Beams
  • Form work
  • Waterproofing/Tanking
  • Structural Engineering
  • Gallery
  • contact
  • projects

This website uses cookies.

We use cookies to analyze website traffic and optimize your website experience. By accepting our use of cookies, your data will be aggregated with all other user data.

DeclineAccept